Wet Dry-Weather Capture and Diversion Project

  • Scope of Work: This project will reduce bacteria and other potential pollutants from entering the Monterey Bay Sanctuary by capturing and diverting stormwater flows west of Lovers Point Park. The captured rainwater will be directed into the sanitary sewer system and directed to Monterey One Water for treatment and reuse. To accomplish this goal the project entails:
    • Installation of 2,858 SF of waste water pipes, and
    • Installation of an underground stormwater capture and diversion tank
  • Project Locations Locations: 
    • ​​​​​​​Ocean View Blvd from 15th St to 19th St
    • ​​​​​​​Ocean View Blvd from Sea Palm Ave to Coral Ave
    • Sea Palm Ave from Del Monte Blvd to Ocean View Blvd
    • Del Monte Blvd from Sea Palm Ave to Egan Ave
  • Construction Timeline:  June 2020 - February 2021

​​​​​​​Sewer Collection System Master Plan Projects 3, 4, 5 & 8

  • Scope of Work: This project will allow for vital sewer infrastructure improvements identified in the City's Sewer Collection System Master Plan (CIP projects 3, 4, 5, & 8). Together, the scope of work for these projects include:
    • Replacement/installation of 4,735 ft of waste water pipe
    • Rehabilitation/replacement of 18 manholes
  • Locations: 
    • Carmel Ave from Ocean View Blvd. to Central Ave
    • Carmel Ave from Pine Ave to Junipero Ave
    • 15th St from Pine Ave to Junipero Ave
    • Asilomar Ave from Ocean View Blvd to Arena Ave
    • Easement from Crocker Ave to Grove Acre
    • Crocker Ave from Arena Ave to Sunset Drive
  • Construction Timeline: June 2020 - December 2020

Phase 8 Sewer Infrastructure Improvements

  •  Scope of Work. This project will allow the City to make important sewer infrastructure improvements including:
    • Replacement of 2,078 LF of sewer line
    • Reconstruction of 8 manholes, and
    • Sewer line spot repairs
  • Project Locations: 
    • 13th Street, between Spruce Ave & Junipero Ave
    • 17 Mile Drive, between Sunset Dr & Weldon Grove Pl
    • Bayview Ave, between Lighthouse Ave & 17 Mile Dr
    • Forest Ave at the David Ave intersection
    • Dennett St, between Sinex Ave & Grove Acre Ave
    • Alder St, between Heacock Ave & Short St
  • Timeline: Construction will begin in September 2020 and is anticipated to conclude in November 2020.
  • Parking & Traffic: Construction notices and "No Parking" signs will be posted in advance of construction. Please expect temporary closures and/or detours during construction.

Pine Ave and Eardley Ave Traffic Calming and Pedestrian Safety Project

  • Scope of Work: The proposed modifications will significantly enhance pedestrian safety by creating a pedestrian refuge area, shortening crossing distances, and slowing traffic. The scope of work includes:
    • Construction of a planter center median and crosswalk
    • Construction of 3 curb ramp bulb-outs
    • 46,500 SF of crack and slurry seal
    • New pavement markings
    • Stormwater improvements including construction of 3 catch basins, 1 storm drain manhole, and 150 LF of stormwater pipe
  • Timing:  Construction will begin in November 2020 and is anticipated to conclude in January 2021.